Following advice from the parish construction consultants, the works have been split into three individual phases consisting of (1) re-wiring, (2) re-roofing, replacing joists, insulation and rainwater goods restoration and (3) secondary glazing to include restoration of the stained-glass window. The reason for this is to increase the pool of potential contractors, following only two interested and qualified bidders on the full Phase 1.
We hope that the rewiring of the hall and the window restoration will be completed over the Easter break with a view to completing the re-roofing, replacing of roof joists, insulation and rainwater goods restoration in late June 2023, over the summer holidays. As always, the campaign for funding proceeds and we would be very grateful, should you not already have done so, if you would consider sponsoring a slate.